[101 Determination of completion date and route for requisitioned sewer or lateral drain]

[101  Determination of completion date and route for requisitioned sewer or lateral drain]

[(1)     A sewerage undertaker shall not be in breach of a duty imposed by section 98 above in relation to any locality or (in the case of a lateral drain) in relation to any premises unless—

(a)     the period of six months beginning with the relevant day has expired; and

(b)     the sewerage undertaker has not, before the end of that period, so laid (as the case may be)—

(i)     the public sewer to be provided as to enable drains and private sewers to be used for the drainage of premises in the locality to communicate with the public sewer; or

(ii)     the lateral drain to be provided as to enable the drain