33 Effect of requirement for development consent on other consent regimes

33  Effect of requirement for development consent on other consent regimes

(1)     To the extent that development consent is required for development, none of the following is required to be obtained for the development or given in relation to it—

(a)     planning permission;

(b)     consent under section 10(1), 11(1) or 12(1) of the Green Belt (London and Home Counties) Act 1938 (c xciii) (erection of buildings and construction of sewer main pipes, watercourses and electric lines etc on Green Belt land);

(c)     a pipe-line construction authorisation under section 1(1) of the Pipe-lines Act 1962 (c 58) (authorisation for construction of cross-country pipe-lines);

(d)     authorisation by an order under section 4(1) of the Gas Act 1965 (c 36) (storage of gas in underground strata);

(e)     . . .

(f)     to the extent that the development relates to land in England, consent under section 2(3) or 3 of the Ancient Monuments and Archaeological Areas Act 1979;

(g)     to the extent that the development relates to land in England, notice under section 35 of the Ancient Monuments and Archaeological Areas Act 1979;

(h)     consent under section 36 or 37 of the Electricity Act 1989 (c 29) (construction etc of generating stations and installation of overhead