[SCHEDULE 5B Reimbursement of Persons Who Have Met Expenses]

[SCHEDULE 5B Reimbursement of Persons Who Have Met Expenses]

[Power to make regulations

1

(1)     The Secretary of State may, by regulations, make provision entitling the relevant electricity distributor to exercise the reimbursement powers in cases where conditions A, B, C and D are met.

(2)     Condition A is met if any electric line or electrical plant is provided for the purpose of making a connection (the “first connectionâ€)—

(a)     between premises and a distribution system, or

(b)     between two distribution systems.

(3)     Condition B is met if a payment in respect of first connection expenses is made by one or more of the following persons—

(a)     a person requiring the first connection in pursuance of section 16(1);

(b)     a person who otherwise causes the first connection to be made (including by means of contractual arrangements).

(4)     Condition C is met if any electric line or electric plant provided for the purpose of making the first connection

Powered by Lexis+®