[32LL The grid or radar delay condition]

[32LL  The grid or radar delay condition]

[(1)     This section applies for the purposes of sections 32LE, 32LG and 32LI.

(2)     The grid or radar delay condition is met in respect of an onshore wind generating station if, on or before the date on which the Authority made its decision to accredit the station, the documents specified in subsection (4), (5) or (6) were—

(a)     submitted by the operator of the station, and

(b)     received by the Authority.

(3)     The grid or radar delay condition is met in respect of additional capacity if, on or before the date on which the Authority made its decision that the additional capacity could form part of an onshore wind generating station, the documents specified in subsection (4), (5) or (6) were—

(a)     submitted by the operator of the station, and

(b)     received by the Authority.

(4)     The documents specified in this subsection are—

(a)     evidence of an agreement with a network operator (“the relevant network operator”) to carry out grid works in relation to the station or additional capacity (“the